Bengaluru

Work begins on Mehkri Circle elevated corridor

Image: The New Indian Express
Type
Infrastructure · Road
Where
Mehkri Circle, Bangalore
Reported
9 November 2026
LOKAZEN DESK2 MIN READBased on reporting by The New Indian Express

The Bangalore Development Authority has started work on the 1.74-km Mehkri Circle elevated corridor and put traffic restrictions in place, even as questions over land acquisition and metro line clearance remain unresolved.

Corridor length
1.74 km
Project cost
Rs 725 crore
Land acquisition budget
Rs 170 crore
Traffic study request to IISc
September 16
IISc proposal submitted
October 21, with a proposed 3-month study period

What's happening

The Bangalore Development Authority (BDA) has begun construction on a 1.74-km elevated corridor at Mehkri Circle in Bengaluru, and traffic restrictions are already in effect around the site.

This is moving ahead even though several technical and land-related questions about the project have not yet been settled, according to the BDA's own responses.

The details

The project is estimated to cost Rs 725 crore, of which Rs 170 crore has been set aside for land acquisition. The BDA said the main elevated structure is planned along the existing Ballari Road corridor, but extra land may still be needed for approach roads, ramps, rotary connections and junction improvements.

The authority said exact locations, survey numbers, the amount of land involved and compensation details would only be confirmed once the approved land acquisition schedule and sanctioned estimate are finalised.

There is also an open question about whether the elevated corridor could clash with Namma Metro's proposed Red Line. The BDA said pier locations, foundations and structural clearances for the corridor need to be checked against BMRCL's alignment drawings, with design changes to be worked out with BMRCL if required, subject to technical feasibility and approval. Final confirmation that there is no interference would depend on approved drawings and BMRCL's technical clearance.

Why it matters

Starting construction before land requirements and metro-corridor clearance are fully worked out leaves open the possibility of later changes to the project's footprint, cost or design.

A Detailed Project Report is said by the BDA to exist, but it is not public, and the authority's own answers suggest some technical aspects are still being examined rather than finalised.

What's next

The BDA asked the Indian Institute of Science (IISc) on September 16 to carry out an independent scientific traffic impact assessment covering both the elevated corridor and the metro project together, treating them as one integrated corridor.

IISc submitted its formal proposal for this study on October 21, suggesting a three-month study period. The BDA said this proposal is still going through administrative and financial approval, even as construction work on the elevated corridor continues.

WHERE IT LANDS

WHAT IT MEANS

Lokazen’s read
  • For brands & retailers

    Construction at Mehkri Circle could disrupt access and footfall for nearby outlets while work is underway.

  • For businesses

    Work at Mehkri Circle could affect road access and commutes for offices whose staff or visitors pass through the junction.

  • For investors & landlords

    Properties reliant on Mehkri Circle access could face a period of construction-related disruption.

HOW TO GET AHEAD

Compare access routes and frontage around Mehkri Circle before committing to nearby space.

Lokazen’s analysis of this report and our location data. A guide for choosing locations, not investment advice.

Looking at Mehkri Circle?

Lokazen maps the brands already trading in Bangalore and the spaces you can lease now.

Keep reading

All moves
All market moves