Issues letter of acceptance for Lucknow Metro Phase-1B underground section

₹1,383.30 crore · 36 months
Image: Metro Rail News
Type
Infrastructure · Metro
Where
Charbagh-Chowk, Lucknow
Reported
10 November 2026
LOKAZEN DESK1 MIN READBased on reporting by Metro Rail News

UPMRC has handed Afcons Infrastructure a ₹1,383.30 crore contract to build the underground Charbagh-Chowk stretch of Lucknow Metro Phase-1B, with 36 months to finish.

Contractor
Afcons Infrastructure Limited
Contract value
₹1,383.30 crore (excluding GST)
Route
Charbagh to ramp after Chowk
LoA date
5 November 2026
Construction period
36 months
Bidders
Five, with Afcons lowest

What's happening

Uttar Pradesh Metro Rail Corporation has issued a letter of acceptance to Afcons Infrastructure Limited for designing and building the underground section of Lucknow Metro Phase-1B, running from Charbagh to the ramp after Chowk.

The details

The contract value stands at ₹1,383.30 crore, excluding GST. UPMRC Managing Director Sushil Kumar signed the letter, which is dated 5 November 2026.

Under the agreement, work begins on the date the letter was issued, and the contractor has 36 months to complete construction, which would place the finish date around November 2029.

Afcons was declared the lowest bidder among five companies after financial bids were opened on 5 October 2026.

Why it matters

The award moves Lucknow Metro Phase-1B forward by locking in both the contractor and the cost for one of its underground stretches, a segment of metro construction that is typically more complex and expensive than elevated sections.

WHERE IT LANDS

WHAT IT MEANS

Lokazen’s read
  • For brands & retailers

    The Charbagh-Chowk underground section could make station-adjacent retail worth watching as the 36-month build progresses.

  • For businesses

    The Charbagh-Chowk section could improve rail access for workplaces along the corridor once operational.

  • For investors & landlords

    A ₹1,383.30 crore underground section over 36 months could focus future commercial interest around Charbagh-Chowk stations.

HOW TO GET AHEAD

Compare retail frontage and office options around Charbagh-Chowk before construction advances.

Lokazen’s analysis of this report and our location data. A guide for choosing locations, not investment advice.

Expanding in Bangalore?

Lokazen maps the brands already trading in Bangalore and the spaces you can lease now.

Keep reading

All moves
All market moves