Road

RIPPL

Sets May 15, 2027 deadline for NH-29 road completion

Type
Infrastructure · Road
Reported
6 November 2026
LOKAZEN DESK1 MIN READBased on reporting by Construction World

Contractor Ratna Infrastructure Project has told a local committee it now aims to finish the stalled Chakhabama-Kikruma stretch of NH-29 in Nagaland by May 15, 2027.

Project
NH-29 Package-II, Chakhabama to Kikruma, Nagaland
Contractor
Ratna Infrastructure Project (RIPPL)
New deadline
May 15, 2027
Original deadline
January 4, 2026
Contract awarded
January 5, 2024
Meeting date
November 2, Kikruma base camp, Phek district

What's happening

Ratna Infrastructure Project, known as RIPPL, has given a fresh completion target of May 15, 2027 for the long-delayed Chakhabama to Kikruma section of National Highway-29 in Nagaland.

The company shared this timeline with the Joint Action Committee of NH-29 during talks held on November 2 at its camp site in Kikruma, within Phek district.

The details

Before the discussion, representatives from the JAC, the company and groups from Kohima, Phek, Meluri and Kiphire walked the Package-II route together, starting from RIPPL's quarry at Chakhabama and finishing at the Kikruma camp.

JAC convenor Vivolie Kezo said the contract had originally been handed to RIPPL on January 5, 2024, with a finish date of January 4, 2026, but claimed several extensions had since been granted even though work was lagging. He also flagged concerns over build quality, saying tender norms were not being followed, and pointed to shortages of equipment, workers, materials and fuel, plus unpaid staff wages, as reasons for the slow pace.

Company signatory Dr MSN Murthy told the panel that quality standards would be upheld and that matters pending with the Ministry of Road Transport and Highways had now been sorted out. He said full-scale construction would pick up soon after November 15, 2026, to meet the ministry's instruction to finish the whole stretch by May 15, 2027.

Why it matters

The committee said it would keep a close watch on progress, having agreed to work with the contractor despite years of frustration over missed deadlines and what it called fading trust among residents.

What's next

The JAC warned that if the May 2027 target is also missed, it will take the matter to higher government authorities.